| Assessment Year | 2001 |
|---|---|
| Principal Product | Plastic Parts |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 196 |
| Plant Area |
159,000
ft2
|
| Annual Production | 13,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $449,590 | 7,919,625 |
kWh
|
$0.057 |
| Electricity Demand | $151,983 | 13,061 |
kW-mo/yr
|
$11.64 |
| Fuel Oil #2 | $12,128 | 1,561 |
MMBtu
|
$7.77 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $55,437 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,278 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $582 | $640 |
$331
8,703
kWh
|
$251
-
kW-mo/yr
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $12,119 | - |
$6,667
175,459
kWh
|
$5,452
-
kW-mo/yr
|
- | - | |
| 03 | 2.4312: Improve lubrication practices | $5,466 | $400 |
$3,750
98,682
kWh
|
$1,716
-
kW-mo/yr
|
- | - | |
| 04 | 3.5316: Contract a wood pallet recycling company | $1,159 | - | - | - | - |
$1,159
-
lb
|
|
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $22,798 | $2,500 | - |
$22,798
-
kW-mo/yr
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $6,128 | $680 |
$6,128
67,814
kWh
|
- | - | - | |
| 07 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $7,185 | $5,520 | - | - |
$7,185
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $55,437 | $9,740 |
$16,876
350,658
kWh
|
$30,217
-
kW-mo/yr
|
$7,185
-
MMBtu
|
$1,159
-
lb
|
||
| TOTAL IMPLEMENTED | $13,278 | - |
$6,667
175,459
kWh
|
$5,452
-
kW-mo/yr
|
- |
$1,159
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs