ITAC Assessment: LE0111
ITAC logo
ITAC Assessment: LE0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Personal Care/Hygienic Film
NAICS
n/a
SIC 3079:
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 94,000
ft2
Annual Production 16,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $432,729 6,336,000
kWh
Electricity Demand $83,399 13,279
kW-mo/yr
Natural Gas $25,448 2,533
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,554 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,711

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $12,514 $2,000 - $12,514
-
kW-mo/yr
-
02 2.2511: Insulate bare equipment $7,197 $323 $6,581
96,782
kWh
$616
-
kW-mo/yr
-
03 2.2511: Insulate bare equipment $5,050 $109 $4,611
67,814
kWh
$439
-
kW-mo/yr
-
04 2.2625: Chill water to the highest temperature possible $7,807 - $7,129
104,832
kWh
$678
-
kW-mo/yr
-
05 2.4221: Install compressor air intakes in coolest locations $986 $1,280 $804
11,827
kWh
$182
-
kW-mo/yr
-
06 3.1162: Use less wasteful packaging $9,000 $7,500 - - $9,000
-
lb
TOTAL RECOMMENDED $42,554 $11,212 $19,125
281,255
kWh
$14,429
-
kW-mo/yr
$9,000
-
lb
TOTAL IMPLEMENTED $19,711 $2,323 $6,581
96,782
kWh
$13,130
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs