Assessment Year | 2000 |
---|---|
Principal Product | custom wood cabinetry |
NAICS |
n/a
|
SIC | 2599: Furniture and Fixtures, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 38 |
Plant Area |
75,000
ft2
|
Annual Production | 35,300
units
|
Production Hrs. Annual | 2,010
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,322 | 665,100 |
kWh
|
$0.038 |
Electricity Demand | $4,671 | 2,658 |
kW-mo/yr
|
$1.76 |
Electricity Fees | $8,514 | - |
|
- |
Natural Gas | $6,720 | 1,090 |
MMBtu
|
$6.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,484 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,132 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $2,352 | $150 |
$1,379
38,101
kWh
|
$711
-
kW-mo/yr
|
- | $262 | - | |
02 | 3.8113: Prevent excessive solvent usage (operator training) | $2,132 | $3,172 | - | - |
$304
-
gal
|
$528 | $1,300 | |
TOTAL RECOMMENDED | $4,484 | $3,322 |
$1,379
38,101
kWh
|
$711
-
kW-mo/yr
|
$304
-
gal
|
$790 | $1,300 | ||
TOTAL IMPLEMENTED | $2,132 | $3,172 | - | - |
$304
-
gal
|
$528 | $1,300 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs