Assessment Year | 2000 |
---|---|
Principal Product | power generation equipment |
NAICS |
n/a
|
SIC | 3621: Motors and Generators |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
129,000
ft2
|
Annual Production | 522,000
units
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $145,199 | 3,488,570 |
kWh
|
$0.042 |
Electricity Demand | $96,991 | 12,262 |
kW-mo/yr
|
$7.91 |
Natural Gas | $13,956 | 7,452 |
MMBtu
|
$1.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,740 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,610 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $12,740 | $4,370 | - | - | $12,740 | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,420 | $15,470 |
$3,230
74,736
kWh
|
$1,310
-
kW-mo/yr
|
- | - | - | $(-120.0) | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,890 | $20 |
$2,030
43,083
kWh
|
$860
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,580 | $1,150 |
$1,950
39,273
kWh
|
$630
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $1,510 | $1,770 | - | - | - |
$1,510
-
MMBtu
|
- | - | - | |
06 | 2.8112: Combine utility meters | $1,450 | $4,000 | - |
$(-6,750.0)
-
kW-mo/yr
|
$8,200 | - | - | - | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,020 | - |
$1,020
16,999
kWh
|
- | - | - | - | - | - | |
08 | 3.1191: Change procedures / equipment / operating conditions | $19,600 | $11,400 | - | - | - | - | - | - | $19,600 | |
09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,530 | $3,000 | - | - | - | - |
$1,530
-
lb
|
- | - | |
TOTAL RECOMMENDED | $47,740 | $41,180 |
$8,230
174,091
kWh
|
$(-3,950.0)
-
kW-mo/yr
|
$20,940 |
$1,510
-
MMBtu
|
$1,530
-
lb
|
$(-120.0) | $19,600 | ||
TOTAL IMPLEMENTED | $26,610 | $26,780 |
$8,230
174,091
kWh
|
$(-3,950.0)
-
kW-mo/yr
|
$20,940 |
$1,510
-
MMBtu
|
- | $(-120.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs