ITAC Assessment: KU0539
ITAC logo
ITAC Assessment: KU0539
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product coffee
NAICS
n/a
SIC 2095: Roasted Coffee
Sales Range $100
M
to 500
M
# of Employees 235
Plant Area 150,000
ft2
Annual Production 100,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $489,342 13,619,871
kWh
Electricity Demand $227,526 26,976
kW-mo/yr
Natural Gas $703,564 232,065
MMBtu
Other Energy $125,455 9,658
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $313,270 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,700

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Water Disposal Savings Personnel Changes Savings
01 2.2437: Recover waste heat from equipment $163,360 $135,000 - - $163,360
-
MMBtu
- - -
02 2.2437: Recover waste heat from equipment $44,700 $30,000 - - $44,700
-
MMBtu
- - -
03 2.2211: Use optimum temperature $15,700 $20,000 - - $15,700
-
MMBtu
- - -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,800 - - $6,800
-
kW-mo/yr
- - - $(-4,000.0)
05 3.4111: Use closed cycle process to minimize waste water production $9,070 $5,750 $(-290.0)
(-11,723)
kWh
$(-380.0)
-
kW-mo/yr
- - $9,740
-
Tgal
-
06 2.1392: Replace purchased steam with other energy source $77,640 $85,000 - - $(-47,810.0)
-
MMBtu
$125,450
-
MMBtu
- -
TOTAL RECOMMENDED $313,270 $275,750 $(-290.0)
(-11,723)
kWh
$6,420
-
kW-mo/yr
$175,950
-
MMBtu
$125,450
-
MMBtu
$9,740
-
Tgal
$(-4,000.0)
TOTAL IMPLEMENTED $15,700 $20,000 - - $15,700
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings Water Disposal Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs