| Assessment Year | 1999 |
|---|---|
| Principal Product | plastic cups and lids |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 135 |
| Plant Area |
250,000
ft2
|
| Annual Production | 250,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $238,666 | 5,605,510 |
kWh
|
$0.043 |
| Electricity Demand | $143,303 | 11,520 |
kW-mo/yr
|
$12.44 |
| Natural Gas | $62,019 | 10,788 |
MMBtu
|
$5.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,620 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2612: Use cooling tower water instead of refrigeration | $5,950 | $9,500 |
$3,840
134,525
kWh
|
$2,110
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,580 | $160 |
$2,500
87,925
kWh
|
$2,080
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4314: Use synthetic lubricant | $2,830 | $5,010 |
$1,200
42,204
kWh
|
$1,000
-
kW-mo/yr
|
- | - | $630 | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,400 | $1,470 |
$280
9,672
kWh
|
$160
-
kW-mo/yr
|
- | $960 | - | - | |
| 05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $12,860 | $18,600 | - | - |
$(-18,520.0)
-
lb
|
- | - | $31,380 | |
| TOTAL RECOMMENDED | $27,620 | $34,740 |
$7,820
274,326
kWh
|
$5,350
-
kW-mo/yr
|
$(-18,520.0)
-
lb
|
$960 | $630 | $31,380 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs