ITAC Assessment: KU0512
ITAC logo
ITAC Assessment: KU0512
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product windows
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 152,000
ft2
Annual Production 8,000,000
lb
Production Hrs. Annual 4,170
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,333 3,198,124
kWh
Electricity Demand $155,031 11,061
kW-mo/yr
Natural Gas $83,867 26,199
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,368,360 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
01 2.2221: Use immersion heating in tanks, melting pots, etc $30,880 $31,230 $13,520
514,068
kWh
$22,780
-
kW-mo/yr
$(-5,420.0)
-
MMBtu
- - - - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $17,150 $28,520 $7,510
285,756
kWh
$12,650
-
kW-mo/yr
$(-3,010.0)
-
MMBtu
- - - - - -
03 2.2426: Use waste heat from flue gases to heat space conditioning air $10,840 $18,000 - - $10,840
-
MMBtu
- - - - - -
04 2.2437: Recover waste heat from equipment $2,640 $810 - - $2,640
-
MMBtu
- - - - - -
05 2.4221: Install compressor air intakes in coolest locations $2,460 $270 $1,010
38,101
kWh
$1,450
-
kW-mo/yr
- - - - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,120 $1,800 $870
32,825
kWh
$1,250
-
kW-mo/yr
- - - - - - -
07 2.2511: Insulate bare equipment $1,520 $1,030 $540
20,516
kWh
$980
-
kW-mo/yr
- - - - - - -
08 2.2531: Re-size charging openings or add movable cover or door $990 $700 - - $990
-
MMBtu
- - - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $550 $770 $140
5,275
kWh
$230
-
kW-mo/yr
- - - $180 - - -
10 3.2121: Convert to electrostatic powder coating $278,220 $513,480 - - $(-13,000.0)
-
MMBtu
- $10,975
-
lb
- $268,330 $11,915 -
11 4.111: Add equipment/ operators to reduce production bottleneck $800,000 $29,240 - - - - - - - - $800,000
12 4.652: Replace existing equipment with more suitable substitutes $220,990 $233,750 - - - $21,790
-
lb
- $199,200 - - -
TOTAL RECOMMENDED $1,368,360 $859,600 $23,590
896,541
kWh
$39,340
-
kW-mo/yr
$(-6,960.0)
-
MMBtu
$21,790
-
lb
$10,975
-
lb
$199,380 $268,330 $11,915 $800,000
TOTAL IMPLEMENTED - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs