| Assessment Year | 1998 |
|---|---|
| Principal Product | remanufactured railroad parts |
| NAICS |
n/a
|
| SIC | 3743: Railroad Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
57,000
ft2
|
| Annual Production | 54,200
pieces
|
| Production Hrs. Annual | 4,280
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,482 | 1,633,353 |
kWh
|
$0.056 |
| Electricity Demand | $24,400 | 4,636 |
kW-mo/yr
|
$5.26 |
| Natural Gas | $24,281 | 3,851 |
MMBtu
|
$6.31 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,850 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,860 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,470 | $7,450 |
$2,050
36,635
kWh
|
$620
-
kW-mo/yr
|
- | $800 | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,750 | $700 |
$2,180
38,980
kWh
|
$570
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7231: Use radiant heater for spot heating | $1,530 | $2,820 | - | - |
$1,530
-
MMBtu
|
- | - | - | |
| 04 | 2.7132: Install timers on light switches in little used areas | $750 | $500 |
$750
13,482
kWh
|
- | - | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $400 | $1,000 |
$320
5,862
kWh
|
$80
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $380 | $420 |
$130
2,345
kWh
|
$20
-
kW-mo/yr
|
- | $230 | - | - | |
| 07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $1,860 | $1,450 | - | - | - | - | - | $1,860 | |
| 08 | 3.8314: Purchase high materials in returnable bulk containers | $1,510 | $940 | - | - | - | - | - | $1,510 | |
| 09 | 4.231: Purchase equipment instead of leasing | $4,200 | $12,000 | - | - | - | - | $4,200 | - | |
| TOTAL RECOMMENDED | $16,850 | $27,280 |
$5,430
97,304
kWh
|
$1,290
-
kW-mo/yr
|
$1,530
-
MMBtu
|
$1,030 | $4,200 | $3,370 | ||
| TOTAL IMPLEMENTED | $8,860 | $14,640 |
$2,500
44,842
kWh
|
$650
-
kW-mo/yr
|
- | - | $4,200 | $1,510 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs