ITAC Assessment: KU0475
ITAC logo
ITAC Assessment: KU0475
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product kitchen and bath cabinetry
NAICS
n/a
SIC 2434: Wood Kitchen Cabinets
Sales Range $5
M
to 10
M
# of Employees 125
Plant Area 36,000
ft2
Annual Production 1,400
units
Production Hrs. Annual 2,600
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,236 693,728
kWh
Electricity Demand $13,098 3,180
kW-mo/yr
Natural Gas $9,655 1,952
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $122,180 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,590

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
01 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $4,260 $30,000 - - $4,260
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,250 $310 $1,720
27,843
kWh
$530
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,290 $5,500 $990
15,826
kWh
$300
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $990 $4,090 $710
11,430
kWh
$280
-
kW-mo/yr
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $820 $230 $590
9,379
kWh
$230
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $490 $250 $490
7,913
kWh
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $360 $480 $160
2,638
kWh
$20
-
kW-mo/yr
- $180 -
08 3.2123: Convert to high volume low pressure (hvlp) paint guns $74,200 $1,500 - - - - $74,200
09 4.711: Initiate a total quality management program $37,520 $11,790 - - - $37,520 -
TOTAL RECOMMENDED $122,180 $54,150 $4,660
75,029
kWh
$1,360
-
kW-mo/yr
$4,260
-
MMBtu
$37,700 $74,200
TOTAL IMPLEMENTED $40,590 $12,330 $2,310
37,222
kWh
$760
-
kW-mo/yr
- $37,520 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs