ITAC Assessment: KU0474
ITAC logo
ITAC Assessment: KU0474
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product commercial turf equipment
NAICS
n/a
SIC 3523: Farm Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 155
Plant Area 136,616
ft2
Annual Production 6,500
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,357 1,876,319
kWh
Electricity Demand $46,674 5,724
kW-mo/yr
Natural Gas $31,172 10,928
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,650 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,590

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,680 $27,070 $1,630
61,841
kWh
$2,050
-
kW-mo/yr
- - - -
02 2.2414: Use waste heat from hot flue gases to preheat $2,490 $6,950 - - $2,490
-
MMBtu
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,270 $190 $1,140
43,083
kWh
$1,130
-
kW-mo/yr
- - - -
04 2.1133: Adjust burners for efficient operation $660 $1,000 $660
70,340
kWh
- - - - -
05 2.4133: Use most efficient type of electric motors $1,350 $4,950 $780
29,894
kWh
$570
-
kW-mo/yr
- - - -
06 2.4221: Install compressor air intakes in coolest locations $460 $210 $50
21,102
kWh
$410
-
kW-mo/yr
- - - -
07 2.7135: Install occupancy sensors $140 $800 $140
5,862
kWh
- - - - -
08 3.5316: Contract a wood pallet recycling company $(-3,710.0) $5,000 - - - - $3,120
-
lb
$(-6,830.0)
09 3.4116: Meter recycled water (to reduce sewer charges) $5,310 $100 - - - $5,310
-
Tgal
- -
TOTAL RECOMMENDED $12,650 $46,270 $4,400
232,122
kWh
$4,160
-
kW-mo/yr
$2,490
-
MMBtu
$5,310
-
Tgal
$3,120
-
lb
$(-6,830.0)
TOTAL IMPLEMENTED $10,590 $40,960 $4,350
211,020
kWh
$3,750
-
kW-mo/yr
$2,490
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs