Assessment Year | 1996 |
---|---|
Principal Product | insulated wire, harnesses, magnetos |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $5 M to 10M |
# of Employees | 65 |
Plant Area |
55,000
ft2
|
Annual Production | 250,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $46,210 | 805,686 |
kWh
|
$0.057 |
Electricity Demand | $10,314 | 3,456 |
kW-mo/yr
|
$2.98 |
Natural Gas | $10,366 | 2,511 |
MMBtu
|
$4.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,079 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,828 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $29,684 | $15,000 | - |
$(-1,046.0)
-
kW-mo/yr
|
- |
$(-6,000.0)
-
lb
|
$(-3,750.0) | $40,480 | |
02 | 3.4115: Recover and reuse cooling water | $4,610 | $8,000 |
$(-1,144.0)
(-19,930)
kWh
|
$(-358.0)
-
kW-mo/yr
|
$6,112
-
gal
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,860 | $191 |
$1,502
26,377
kWh
|
$358
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $582 | $700 |
$450
7,913
kWh
|
$132
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2511: Insulate bare equipment | $566 | $444 |
$432
7,620
kWh
|
$134
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $526 | $137 |
$425
7,327
kWh
|
$101
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $251 | $360 |
$114
2,052
kWh
|
$137
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $38,079 | $24,832 |
$1,779
31,359
kWh
|
$(-542.0)
-
kW-mo/yr
|
$6,112
-
gal
|
$(-6,000.0)
-
lb
|
$(-3,750.0) | $40,480 | ||
TOTAL IMPLEMENTED | $37,828 | $24,472 |
$1,665
29,307
kWh
|
$(-679.0)
-
kW-mo/yr
|
$6,112
-
gal
|
$(-6,000.0)
-
lb
|
$(-3,750.0) | $40,480 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs