| Assessment Year | 1994 |
|---|---|
| Principal Product | Commercial lawnmowers |
| NAICS |
n/a
|
| SIC | 3523: Farm Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 96 |
| Plant Area |
87,000
ft2
|
| Annual Production | 9,000
pieces
|
| Production Hrs. Annual | 2,184
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $47,387 | 818,875 |
kWh
|
$0.058 |
| Natural Gas | $36,128 | 9,280 |
MMBtu
|
$3.89 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,108 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7145: Install skylights | $7,072 | $35,400 |
$7,072
122,216
kWh
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,001 | $8,058 |
$2,001
34,584
kWh
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,523 | $4,449 |
$865
14,947
kWh
|
- | $658 | - | |
| 04 | 2.7135: Install occupancy sensors | $390 | $900 |
$390
6,741
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $381 | $360 |
$153
2,638
kWh
|
- | $228 | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $179 | $325 |
$102
1,758
kWh
|
- | - | $77 | |
| 07 | 2.2437: Recover waste heat from equipment | $2,066 | $9,950 | - |
$2,066
-
MMBtu
|
- | - | |
| 08 | 2.2437: Recover waste heat from equipment | $2,058 | $2,075 | - |
$2,058
-
MMBtu
|
- | - | |
| 09 | 2.2437: Recover waste heat from equipment | $1,195 | $8,640 |
$(-594.0)
(-10,258)
kWh
|
$1,789
-
MMBtu
|
- | - | |
| 10 | 2.7224: Reduce space conditioning during non-working hours | $435 | $400 |
$322
5,569
kWh
|
$113
-
MMBtu
|
- | - | |
| 11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $271 | $130 |
$271
4,689
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $17,571 | $70,687 |
$10,582
182,884
kWh
|
$6,026
-
MMBtu
|
$886 | $77 | ||
| TOTAL IMPLEMENTED | $8,108 | $26,329 |
$1,119
19,343
kWh
|
$6,026
-
MMBtu
|
$886 | $77 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs