| Assessment Year | 1993 |
|---|---|
| Principal Product | Children's Clothing |
| NAICS |
n/a
|
| SIC | 2369: Girls', Children's, and Infants' Outerwear, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
110,000
ft2
|
| Annual Production | 40,000,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $132,529 | 2,107,855 |
kWh
|
$0.063 |
| Natural Gas | $26,711 | 6,763 |
MMBtu
|
$3.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,089 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $24,271 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.5111: Convert from indirect to direct fired systems | $10,634 | $11,960 |
$10,634
169,109
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,539 | $8,930 |
$10,539
97,304
kWh
|
- | |
| 03 | 2.7124: Make a practice of turning off lights when not needed | $663 | - |
$663
10,551
kWh
|
- | |
| 04 | 2.2515: Use optimum thickness insulation | $5,818 | $3,721 |
$6,782
107,855
kWh
|
$(-964.0)
-
MMBtu
|
|
| 05 | 2.6218: Turn off equipment when not in use | $1,106 | $1,350 |
$1,106
17,585
kWh
|
- | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $625 | $780 |
$625
9,379
kWh
|
- | |
| 07 | 2.2437: Recover waste heat from equipment | $518 | $678 |
$(-39.0)
(-586)
kWh
|
$557
-
MMBtu
|
|
| 08 | 2.6121: Reduce hot water temperature to the minimum required | $186 | - | - |
$186
-
MMBtu
|
|
| TOTAL RECOMMENDED | $30,089 | $27,419 |
$30,310
411,197
kWh
|
$(-221.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $24,271 | $23,698 |
$23,528
303,342
kWh
|
$743
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs