ITAC Assessment: KU0404
ITAC logo
ITAC Assessment: KU0404
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Children's Clothing
NAICS
n/a
SIC 2369: Girls', Children's, and Infants' Outerwear, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 110,000
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,529 2,107,855
kWh
Natural Gas $26,711 6,763
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,089 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,271

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.5111: Convert from indirect to direct fired systems $10,634 $11,960 $10,634
169,109
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,539 $8,930 $10,539
97,304
kWh
-
03 2.7124: Make a practice of turning off lights when not needed $663 - $663
10,551
kWh
-
04 2.2515: Use optimum thickness insulation $5,818 $3,721 $6,782
107,855
kWh
$(-964.0)
-
MMBtu
05 2.6218: Turn off equipment when not in use $1,106 $1,350 $1,106
17,585
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $625 $780 $625
9,379
kWh
-
07 2.2437: Recover waste heat from equipment $518 $678 $(-39.0)
(-586)
kWh
$557
-
MMBtu
08 2.6121: Reduce hot water temperature to the minimum required $186 - - $186
-
MMBtu
TOTAL RECOMMENDED $30,089 $27,419 $30,310
411,197
kWh
$(-221.0)
-
MMBtu
TOTAL IMPLEMENTED $24,271 $23,698 $23,528
303,342
kWh
$743
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs