| Assessment Year | 1989 |
|---|---|
| Principal Product | SEALED LEAD BATTERIES |
| NAICS |
n/a
|
| SIC | 3691: Storage Batteries |
| Sales Range | $10 M to 50M |
| # of Employees | 450 |
| Plant Area |
n/a
|
| Annual Production | 12,500,000
pieces
|
| Production Hrs. Annual | 6,072
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $760,904 | 16,055,100 |
kWh
|
$0.047 |
| Natural Gas | $105,954 | 28,387 |
MMBtu
|
$3.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,265 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $903 | $472 |
$903
19,050
kWh
|
- | - | |
| 02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $16,418 | $15,000 |
$16,418
346,424
kWh
|
- | - | |
| 03 | 2.2621: Modify refrigeration system to operate at a lower pressure | $7,667 | $8,200 |
$7,667
161,782
kWh
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,153 | $4,100 |
$4,153
87,632
kWh
|
- | - | |
| 05 | 2.2511: Insulate bare equipment | $1,104 | $600 | - |
$1,104
-
MMBtu
|
- | |
| 06 | 2.2437: Recover waste heat from equipment | $526 | $200 | - |
$526
-
MMBtu
|
- | |
| 07 | 2.6218: Turn off equipment when not in use | $579 | - | - |
$679
-
MMBtu
|
$(-100.0) | |
| TOTAL RECOMMENDED | $31,350 | $28,572 |
$29,141
614,888
kWh
|
$2,309
-
MMBtu
|
$(-100.0) | ||
| TOTAL IMPLEMENTED | $7,265 | $5,372 |
$5,056
106,682
kWh
|
$2,309
-
MMBtu
|
$(-100.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs