Assessment Year | 1989 |
---|---|
Principal Product | SEALED LEAD BATTERIES |
NAICS |
n/a
|
SIC | 3691: Storage Batteries |
Sales Range | $10 M to 50M |
# of Employees | 450 |
Plant Area |
n/a
|
Annual Production | 12,500,000
pieces
|
Production Hrs. Annual | 6,072
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $760,904 | 16,055,100 |
kWh
|
$0.047 |
Natural Gas | $105,954 | 28,387 |
MMBtu
|
$3.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,265 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $903 | $472 |
$903
19,050
kWh
|
- | - | |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $16,418 | $15,000 |
$16,418
346,424
kWh
|
- | - | |
03 | 2.2621: Modify refrigeration system to operate at a lower pressure | $7,667 | $8,200 |
$7,667
161,782
kWh
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $4,153 | $4,100 |
$4,153
87,632
kWh
|
- | - | |
05 | 2.2511: Insulate bare equipment | $1,104 | $600 | - |
$1,104
-
MMBtu
|
- | |
06 | 2.2437: Recover waste heat from equipment | $526 | $200 | - |
$526
-
MMBtu
|
- | |
07 | 2.6218: Turn off equipment when not in use | $579 | - | - |
$679
-
MMBtu
|
$(-100.0) | |
TOTAL RECOMMENDED | $31,350 | $28,572 |
$29,141
614,888
kWh
|
$2,309
-
MMBtu
|
$(-100.0) | ||
TOTAL IMPLEMENTED | $7,265 | $5,372 |
$5,056
106,682
kWh
|
$2,309
-
MMBtu
|
$(-100.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs