Assessment Year | 1988 |
---|---|
Principal Product | BOOTHS, SIGNS & DISPLAYS |
NAICS |
n/a
|
SIC | 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
n/a
|
Annual Production | 66,374
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,233 | 1,796,014 |
kWh
|
$0.067 |
Natural Gas | $78,599 | 20,032 |
MMBtu
|
$3.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $56,193 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,307 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $20,271 | $2,500 | - |
$19,475
-
MMBtu
|
$796 | |
02 | 3.4115: Recover and reuse cooling water | $19,728 | $9,000 |
$882
13,189
kWh
|
- | $18,846 | |
03 | 2.8121: Apply for tax-free status for energy purchases | $4,505 | - |
$4,505
-
kWh
|
- | - | |
04 | 2.2514: Cover open tanks | $2,897 | $600 | - |
$2,897
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,471 | $150 |
$2,471
36,928
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,843 | $2,961 |
$1,843
27,550
kWh
|
- | - | |
07 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $1,435 | $267 |
$137
2,052
kWh
|
$1,298
-
MMBtu
|
- | |
08 | 2.7224: Reduce space conditioning during non-working hours | $988 | $14 |
$353
5,275
kWh
|
$635
-
MMBtu
|
- | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $608 | $40 |
$608
9,086
kWh
|
- | - | |
10 | 2.2136: Install / repair insulation on steam lines | $545 | $850 | - |
$545
-
MMBtu
|
- | |
11 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $451 | $450 |
$569
8,499
kWh
|
$(-118.0)
-
MMBtu
|
- | |
12 | 2.4312: Improve lubrication practices | $275 | - |
$275
4,103
kWh
|
- | - | |
13 | 2.6121: Reduce hot water temperature to the minimum required | $176 | - |
$176
2,638
kWh
|
- | - | |
TOTAL RECOMMENDED | $56,193 | $16,832 |
$11,819
109,320
kWh
|
$24,732
-
MMBtu
|
$19,642 | ||
TOTAL IMPLEMENTED | $54,307 | $16,115 |
$11,113
98,769
kWh
|
$23,552
-
MMBtu
|
$19,642 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs