| Assessment Year | 1988 |
|---|---|
| Principal Product | ALUMINUM EXTRUSIONS |
| NAICS |
n/a
|
| SIC | 3354: Aluminum Extruded Products |
| Sales Range | $1 M to 5M |
| # of Employees | 50 |
| Plant Area |
n/a
|
| Annual Production | 3,000,000
lb
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $173,657 | 1,733,587 |
kWh
|
$0.10 |
| Natural Gas | $56,698 | 15,123 |
MMBtu
|
$3.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $43,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $42,903 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $33,489 | $50,000 |
$39,857
398,007
kWh
|
$(-6,368.0)
-
MMBtu
|
- | |
| 03 | 2.2443: Re-use or recycle hot or cold process exhaust air | $3,396 | $4,000 | - |
$3,446
-
MMBtu
|
$(-50.0) | |
| 04 | 2.2514: Cover open tanks | $2,670 | $400 | - |
$2,670
-
MMBtu
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $311 | $162 |
$311
3,517
kWh
|
- | - | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $760 | - | - |
$810
-
MMBtu
|
$(-50.0) | |
| 07 | 2.1222: Install turbulators | $724 | $960 | - |
$724
-
MMBtu
|
- | |
| 08 | 2.2511: Insulate bare equipment | $656 | $840 | - |
$656
-
MMBtu
|
- | |
| 09 | 2.2136: Install / repair insulation on steam lines | $518 | $250 | - |
$518
-
MMBtu
|
- | |
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $499 | - |
$499
4,982
kWh
|
- | - | |
| 11 | 2.1123: Install automatic stack damper | $398 | $700 | - |
$398
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $43,421 | $57,312 |
$40,667
406,506
kWh
|
$2,854
-
MMBtu
|
$(-100.0) | ||
| TOTAL IMPLEMENTED | $42,903 | $57,062 |
$40,667
406,506
kWh
|
$2,336
-
MMBtu
|
$(-100.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs