| Assessment Year | 1987 |
|---|---|
| Principal Product | BALL BEARINGS |
| NAICS |
n/a
|
| SIC | 3562: Ball and Roller Bearings |
| Sales Range | $10 M to 50M |
| # of Employees | 245 |
| Plant Area |
n/a
|
| Annual Production | 35,000,000
pieces
|
| Production Hrs. Annual | 5,688
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $484,117 | 10,810,961 |
kWh
|
$0.045 |
| Natural Gas | $88,018 | 25,330 |
MMBtu
|
$3.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,830 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4312: Improve lubrication practices | $11,769 | - |
$11,769
262,896
kWh
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,844 | - |
$3,844
85,873
kWh
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $3,582 | $400 |
$3,582
80,012
kWh
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $2,242 | $4,000 | - |
$2,242
-
MMBtu
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,629 | - | - |
$1,829
-
MMBtu
|
$(-200.0) | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $935 | $1,800 |
$1,299
29,015
kWh
|
$(-364.0)
-
MMBtu
|
- | |
| 07 | 2.1123: Install automatic stack damper | $784 | $1,275 | - |
$784
-
MMBtu
|
- | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $524 | - | - |
$684
-
MMBtu
|
$(-160.0) | |
| 09 | 2.2511: Insulate bare equipment | $643 | $150 |
$643
14,361
kWh
|
- | - | |
| 10 | 2.6214: Shut off pilots in standby equipment | $162 | - | - |
$222
-
MMBtu
|
$(-60.0) | |
| 11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $131 | $50 |
$131
2,931
kWh
|
- | - | |
| TOTAL RECOMMENDED | $26,245 | $7,675 |
$21,268
475,088
kWh
|
$5,397
-
MMBtu
|
$(-420.0) | ||
| TOTAL IMPLEMENTED | $9,830 | $4,400 |
$7,426
165,885
kWh
|
$2,464
-
MMBtu
|
$(-60.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs