ITAC Assessment: KU0220
ITAC logo
ITAC Assessment: KU0220
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product TRANSFORMERS & INDUCTORS
NAICS
n/a
SIC 3677: Electronic Coils, Transformers, and Other Inductors
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 1,000,000
pieces
Production Hrs. Annual 2,581
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $56,824 881,008
kWh
Natural Gas $3,196 786
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,986 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,755

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,362 $3,200 $2,362
36,635
kWh
-
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,475 $600 $1,908
29,601
kWh
$(-433.0)
-
MMBtu
03 2.6121: Reduce hot water temperature to the minimum required $280 - - $280
-
MMBtu
04 2.2514: Cover open tanks $756 $70 $756
11,723
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $113 $10 $113
1,758
kWh
-
TOTAL RECOMMENDED $4,986 $3,880 $5,139
79,717
kWh
$(-153.0)
-
MMBtu
TOTAL IMPLEMENTED $2,755 $3,210 $2,475
38,393
kWh
$280
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs