Assessment Year | 1986 |
---|---|
Principal Product | TRUCK BODIES & TRAILERS |
NAICS |
n/a
|
SIC | 3713: Truck and Bus Bodies |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 650
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $64,095 | 739,156 |
kWh
|
$0.087 |
Natural Gas | $24,587 | 5,508 |
MMBtu
|
$4.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,044 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,919 | $6,173 |
$8,919
102,872
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,324 | $6,000 |
$5,539
63,892
kWh
|
$(-1,215.0)
-
MMBtu
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $1,330 | $100 |
$1,330
15,240
kWh
|
- | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,289 | $100 | - |
$1,289
-
MMBtu
|
- | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $906 | $34 |
$152
1,758
kWh
|
$754
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $600 | $200 |
$600
7,034
kWh
|
- | - | |
07 | 2.1232: Keep boiler tubes clean | $112 | $100 | - |
$162
-
MMBtu
|
$(-50.0) | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $80 | - | - |
$130
-
MMBtu
|
$(-50.0) | |
TOTAL RECOMMENDED | $17,560 | $12,707 |
$16,540
190,796
kWh
|
$1,120
-
MMBtu
|
$(-100.0) | ||
TOTAL IMPLEMENTED | $13,044 | $6,607 |
$11,001
126,904
kWh
|
$2,043
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs