| Assessment Year | 1984 |
|---|---|
| Principal Product | OPTICAL MEASURING EQUIPMENT |
| NAICS |
n/a
|
| SIC | 3826: Laboratory Analytical Instruments |
| Sales Range | $1 M to 5M |
| # of Employees | 70 |
| Plant Area |
n/a
|
| Annual Production | 5,000
pieces
|
| Production Hrs. Annual | 2,730
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,840 | 800,117 |
kWh
|
$0.070 |
| Natural Gas | $6,659 | 1,354 |
MMBtu
|
$4.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $9,837 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,499 | $5,941 |
$4,499
64,478
kWh
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $1,988 | $3,000 | - |
$1,988
-
MMBtu
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $818 | $100 |
$818
11,723
kWh
|
- | - | |
| 04 | 2.3191: Use demand controller or load shedder | $1,181 | $1,600 |
$1,181
-
kWh
|
- | - | |
| 05 | 2.4312: Improve lubrication practices | $593 | $500 |
$593
8,499
kWh
|
- | - | |
| 06 | 2.1123: Install automatic stack damper | $389 | $500 | - |
$389
-
MMBtu
|
- | |
| 07 | 2.6214: Shut off pilots in standby equipment | $103 | - | - |
$113
-
MMBtu
|
$(-10.0) | |
| 08 | 2.6121: Reduce hot water temperature to the minimum required | $118 | - | - |
$118
-
MMBtu
|
- | |
| 09 | 2.2511: Insulate bare equipment | $148 | $64 | - |
$148
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $9,837 | $11,705 |
$7,091
84,700
kWh
|
$2,756
-
MMBtu
|
$(-10.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs