Assessment Year | 1984 |
---|---|
Principal Product | OPTICAL MEASURING EQUIPMENT |
NAICS |
n/a
|
SIC | 3826: Laboratory Analytical Instruments |
Sales Range | $1 M to 5M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 5,000
pieces
|
Production Hrs. Annual | 2,730
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,840 | 800,117 |
kWh
|
$0.070 |
Natural Gas | $6,659 | 1,354 |
MMBtu
|
$4.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,837 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,499 | $5,941 |
$4,499
64,478
kWh
|
- | - | |
02 | 2.2437: Recover waste heat from equipment | $1,988 | $3,000 | - |
$1,988
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $818 | $100 |
$818
11,723
kWh
|
- | - | |
04 | 2.3191: Use demand controller or load shedder | $1,181 | $1,600 |
$1,181
-
kWh
|
- | - | |
05 | 2.4312: Improve lubrication practices | $593 | $500 |
$593
8,499
kWh
|
- | - | |
06 | 2.1123: Install automatic stack damper | $389 | $500 | - |
$389
-
MMBtu
|
- | |
07 | 2.6214: Shut off pilots in standby equipment | $103 | - | - |
$113
-
MMBtu
|
$(-10.0) | |
08 | 2.6121: Reduce hot water temperature to the minimum required | $118 | - | - |
$118
-
MMBtu
|
- | |
09 | 2.2511: Insulate bare equipment | $148 | $64 | - |
$148
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $9,837 | $11,705 |
$7,091
84,700
kWh
|
$2,756
-
MMBtu
|
$(-10.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs