Assessment Year | 1981 |
---|---|
Principal Product | BUILDING COMPONENTS |
NAICS |
n/a
|
SIC | 2452: Prefabricated Wood Buildings and Components |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
n/a
|
Annual Production | 30,000
pieces
|
Production Hrs. Annual | 2,024
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $30,762 | 549,238 |
kWh
|
$0.056 |
Natural Gas | $11,667 | 4,041 |
MMBtu
|
$2.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,051 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $325 | - |
$66
1,172
kWh
|
$259
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,428 | $3,992 |
$4,428
79,132
kWh
|
- | |
03 | 2.6121: Reduce hot water temperature to the minimum required | $298 | - |
$80
1,465
kWh
|
$218
-
MMBtu
|
|
TOTAL RECOMMENDED | $5,051 | $3,992 |
$4,574
81,769
kWh
|
$477
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs