ITAC Assessment: KU0028
ITAC logo
ITAC Assessment: KU0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1981
Principal Product BUILDING COMPONENTS
NAICS
n/a
SIC 2452: Prefabricated Wood Buildings and Components
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 30,000
pieces
Production Hrs. Annual 2,024
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,762 549,238
kWh
Natural Gas $11,667 4,041
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,051 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $325 - $66
1,172
kWh
$259
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,428 $3,992 $4,428
79,132
kWh
-
03 2.6121: Reduce hot water temperature to the minimum required $298 - $80
1,465
kWh
$218
-
MMBtu
TOTAL RECOMMENDED $5,051 $3,992 $4,574
81,769
kWh
$477
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs