| Assessment Year | 1981 |
|---|---|
| Principal Product | CONCRETE BLOCK |
| NAICS |
n/a
|
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $1 M to 5M |
| # of Employees | 16 |
| Plant Area |
n/a
|
| Annual Production | 1,500,000
pieces
|
| Production Hrs. Annual | 2,750
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $12,757 | 242,087 |
kWh
|
$0.053 |
| Natural Gas | $18,258 | 7,183 |
MMBtu
|
$2.54 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $2,574 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2441: Preheat boiler makeup water with waste process heat | $1,669 | $2,600 | - |
$1,669
-
MMBtu
|
|
| 02 | 2.7261: Install timers and/or thermostats | $556 | - |
$74
1,465
kWh
|
$482
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $349 | $357 |
$349
6,741
kWh
|
- | |
| TOTAL RECOMMENDED | $2,574 | $2,957 |
$423
8,206
kWh
|
$2,151
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs