Assessment Year | 1981 |
---|---|
Principal Product | CONCRETE BLOCK |
NAICS |
n/a
|
SIC | 3271: Concrete Block and Brick |
Sales Range | $1 M to 5M |
# of Employees | 16 |
Plant Area |
n/a
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $12,757 | 242,087 |
kWh
|
$0.053 |
Natural Gas | $18,258 | 7,183 |
MMBtu
|
$2.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,574 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2441: Preheat boiler makeup water with waste process heat | $1,669 | $2,600 | - |
$1,669
-
MMBtu
|
|
02 | 2.7261: Install timers and/or thermostats | $556 | - |
$74
1,465
kWh
|
$482
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $349 | $357 |
$349
6,741
kWh
|
- | |
TOTAL RECOMMENDED | $2,574 | $2,957 |
$423
8,206
kWh
|
$2,151
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs