ITAC Assessment: KS2649
ITAC logo
ITAC Assessment: KS2649
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Car Metal Part Stamping
NAICS 336370: Motor Vehicle Metal Stamping
SIC 3465: Automotive Stampings
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 400,000
ft2
Annual Production 750,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,028,997 14,627,098
kWh
Natural Gas $73,562 5,364
MMBtu
Waste Disposal Costs
Water Usage $14,551 3,504
Tgal
Water Disposal $7,959 3,504
Tgal
TOTAL YEARLY COSTS $1,125,069
RECOMMENDED SAVINGS* $168,257 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $13,890 $6,920 $13,890
198,431
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $3,304 $60 $3,304
43,341
kWh
-
03 2.2449: Recover heat from exhausted steam, hot air or hot water $14,554 $10,760 - $14,554
-
MMBtu
04 2.7134: Use photocell controls $720 $4,700 $720
10,283
kWh
-
05 2.9114: Use solar heat to make electricty $135,789 $1,778,000 $135,789
1,939,846
kWh
-
TOTAL RECOMMENDED $168,257 $1,800,440 $153,703
2,191,901
kWh
$14,554
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs