ITAC Assessment: KS2431
ITAC logo
ITAC Assessment: KS2431
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Yarn and Rugs
NAICS 314110: Carpet and Rug Mills
SIC 2273: Carpets and Rugs
Sales Range $50
M
to 100
M
# of Employees 175
Plant Area 550,000
ft2
Annual Production 40,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,241,801 22,644,003
kWh
Electricity Demand $577,168 45,146
kW-mo/yr
Natural Gas $10,810 1,134
MMBtu
Waste Disposal Costs
Water Usage $711 117
Tgal
Water Disposal $360 117
Tgal
TOTAL YEARLY COSTS $1,830,849
RECOMMENDED SAVINGS* $150,329 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $37,021 $362,701 $28,382
516,045
kWh
$8,639
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,373 $5,480 $2,331
42,378
kWh
$1,042
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $46,895 $154,122 $20,420
371,280
kWh
$9,125
-
kW-mo/yr
$17,350
04 2.7135: Install occupancy sensors $10,405 $31,750 $6,435
117,000
kWh
- $3,970
05 2.7232: Replace existing hvac unit with high efficiency model $52,635 $494,620 $36,379
661,440
kWh
$16,256
-
kW-mo/yr
-
TOTAL RECOMMENDED $150,329 $1,048,673 $93,947
1,708,143
kWh
$35,062
-
kW-mo/yr
$21,320
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs