Assessment Year | 2024 |
---|---|
Principal Product | Corrugated Board |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 153 |
Plant Area |
185,000
ft2
|
Annual Production | 646,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $412,194 | 6,713,853 |
kWh
|
$0.061 | |
Electricity Demand | $202,001 | 13,214 |
kW-mo/yr
|
$15.29 | |
Natural Gas | $277,478 | 66,418 |
MMBtu
|
$4.18 | |
Waste Disposal Costs | |||||
Water Usage | $31,671 | 4,526 |
Tgal
|
$7.00 | |
Water Disposal | $48,244 | 4,526 |
Tgal
|
$10.66 | |
TOTAL YEARLY COSTS | $971,588 | ||||
RECOMMENDED SAVINGS* | $173,359 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $53,570 | $460,976 |
$40,437
662,902
kWh
|
$13,133
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,137 | $60 |
$1,739
28,514
kWh
|
$1,398
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,174 | $9,216 |
$767
12,580
kWh
|
$370
-
kW-mo/yr
|
- | $1,037 | |
04 | 2.2136: Install / repair insulation on steam lines | $4,172 | $5,121 | - | - |
$4,172
-
MMBtu
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $16,954 | $60,601 | - | - |
$16,954
-
MMBtu
|
- | |
06 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $93,352 | $684,000 |
$76,128
1,248,000
kWh
|
$36,720
-
kW-mo/yr
|
$(-13,096.0)
-
MMBtu
|
$(-6,400.0) | |
TOTAL RECOMMENDED | $173,359 | $1,219,974 |
$119,071
1,951,996
kWh
|
$51,621
-
kW-mo/yr
|
$8,030
-
MMBtu
|
$(-5,363.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs