ITAC Assessment: KS2320
ITAC logo
ITAC Assessment: KS2320
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Aluminum Parts of Vehicles
NAICS 336211: Motor Vehicle Body Manufacturing
SIC 3711: Motor Vehicles and Passenger Car Bodies
Sales Range $100
M
to 500
M
# of Employees 198
Plant Area 125,000
ft2
Annual Production 5,000,000
pieces
Production Hrs. Annual 5,800
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $606,724 6,674,250
kWh
Natural Gas $73,703 4,694
MMBtu
Waste Disposal Costs
Water Usage $7,726 1,018
Tgal
Water Disposal $7,726 1,018
Tgal
TOTAL YEARLY COSTS $695,879
RECOMMENDED SAVINGS* $71,823 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.2522: Isolate hot or cold equipment $5,723 $1,804 $5,723
62,889
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,340 $60 $1,340
14,729
kWh
-
03 2.6212: Turn off equipment during breaks, reduce operating time $5,903 - $5,903
64,867
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,227 $16,176 $2,217
24,360
kWh
$2,010
05 2.9114: Use solar heat to make electricty $54,630 $421,943 $54,630
600,331
kWh
-
TOTAL RECOMMENDED $71,823 $439,983 $69,813
767,176
kWh
$2,010
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs