ITAC Assessment: KS2209
ITAC logo
ITAC Assessment: KS2209
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Appliance Metal Hardware
NAICS 332510: Hardware Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 326
Plant Area 180,000
ft2
Annual Production 18,000,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $512,825 5,125,355
kWh
Natural Gas $139,221 25,229
MMBtu
Waste Disposal Costs
Water Usage $37,730 3,499
Tgal
Water Disposal $34,068 3,499
Tgal
TOTAL YEARLY COSTS $723,844
RECOMMENDED SAVINGS* $209,940 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $110,725

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $24,875 $1,600 - - $6,219 $18,656
02 2.8123: Pay utility bills on time $593 - - - $593 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,552 $5,960 $12,552
125,515
kWh
- - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $4,315 $60 $4,315
43,146
kWh
- - -
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,610 $1,085 $2,610
26,100
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $8,163 $34,256 $5,600
56,000
kWh
- $2,563 -
07 2.9114: Use solar heat to make electricty $77,094 $526,518 $77,094
770,943
kWh
- - -
08 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $79,738 $627,000 $100,000
1,000,000
kWh
$(-13,862.0)
-
MMBtu
$(-6,400.0) -
TOTAL RECOMMENDED $209,940 $1,196,479 $202,171
2,021,704
kWh
$(-13,862.0)
-
MMBtu
$2,975 $18,656
TOTAL IMPLEMENTED $110,725 $562,374 $82,694
826,943
kWh
- $9,375 $18,656
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs