Assessment Year | 1995 |
---|---|
Principal Product | Semi-finished and finished truck trailer stock |
NAICS |
n/a
|
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $10 M to 50M |
# of Employees | 47 |
Plant Area |
n/a
|
Annual Production | 6,000
thousand feet
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,714 | 1,054,513 |
kWh
|
$0.083 |
Natural Gas | $40,999 | 18,218 |
MMBtu
|
$2.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,576 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,576 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,440 | $4,020 |
$7,440
71,512
kWh
|
- | |
02 | 2.7124: Make a practice of turning off lights when not needed | $630 | - |
$630
24,326
kWh
|
- | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $330 | - |
$330
12,603
kWh
|
- | |
04 | 2.2511: Insulate bare equipment | $100 | $25 | - |
$100
-
MMBtu
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $76 | $100 |
$76
2,931
kWh
|
- | |
TOTAL RECOMMENDED | $8,576 | $4,145 |
$8,476
111,372
kWh
|
$100
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,576 | $4,145 |
$8,476
111,372
kWh
|
$100
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs