Assessment Year | 1997 |
---|---|
Principal Product | Soft drink and juice dispensers |
NAICS |
n/a
|
SIC | 3685: |
Sales Range | $50 M to 100M |
# of Employees | 475 |
Plant Area |
325,000
ft2
|
Annual Production | 4,500
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $194,561 | 6,161,782 |
kWh
|
$0.032 |
Electricity Demand | $92,166 | 13,737 |
kW-mo/yr
|
$6.71 |
Electricity Fees | $1,740 | - |
|
- |
Natural Gas | $6,143 | 1,427 |
MMBtu
|
$4.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,060 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $5,748 | - | n/a |
$5,748
183,177
kWh
|
- | - | - |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,204 | $1,620 | n/a |
$1,953
62,134
kWh
|
$1,251
-
kW-mo/yr
|
- | - |
03 | 2.2511: Insulate bare equipment | $2,094 | $519 | n/a |
$2,094
66,530
kWh
|
- | - | - |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,444 | $4,133 | n/a |
$1,444
48,066
kWh
|
- | - | - |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,325 | $150 | n/a |
$949
30,188
kWh
|
$376
-
kW-mo/yr
|
- | - |
06 | 2.2611: Moderate cooling tower outlet temperature | $870 | $60 | n/a |
$870
27,550
kWh
|
- | - | - |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $178 | $352 | n/a |
$178
5,569
kWh
|
- | - | - |
08 | 3.5313: Increase amount of waste recovered for resale | $270 | $38 | n/a | - | - |
$270
-
lb
|
- |
09 | 4.423: Move product using mechanical means | $22,327 | $11,750 | n/a | - | - | - | $22,327 |
10 | 4.431: Train operators for maximum operating efficiency | $39,600 | $6,000 | n/a | - | - | - | $39,600 |
TOTAL RECOMMENDED | $77,060 | $24,622 |
$13,236
423,214
kWh
|
$1,627
-
kW-mo/yr
|
$270
-
lb
|
$61,927 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs