ITAC Assessment: KG0059
ITAC logo
ITAC Assessment: KG0059
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Seafood processing and fresh produce freezing
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $1
M
to 5
M
# of Employees 105
Plant Area 130,000
ft2
Annual Production 185,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $190,957 8,219,226
kWh
Electricity Demand $206,521 15,705
kW-mo/yr
Electricity Fees $257 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $101,258 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings
01 2.2626: Avoid frost formation on evaporators $65,997 $15,000 $48,429
1,076,495
kWh
$17,568
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $7,609 $23,780 $4,888
222,157
kWh
$2,721
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,522 $2,500 $1,423
64,771
kWh
$2,099
-
kW-mo/yr
- -
04 3.4113: Treat and reuse rinse waters $18,341 $2,930 - - $18,341
-
Tgal
-
05 3.5212: Regrind, reuse, or sell scrap plastic parts $5,789 $3,000 - - - $5,789
-
lb
TOTAL RECOMMENDED $101,258 $47,210 $54,740
1,363,423
kWh
$22,388
-
kW-mo/yr
$18,341
-
Tgal
$5,789
-
lb
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs