ITAC Assessment: KG0039
ITAC logo
ITAC Assessment: KG0039
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Carbon Interveaved Forms,Continuous Forms
NAICS
n/a
SIC 2751:
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 12,500
ft2
Annual Production 500,000
lb
Production Hrs. Annual 2,574
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,509 550,996
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,563 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $411

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.3134: Shift from daytime to nighttime operation $4,935 - $4,935
-
kWh
02 2.4314: Use synthetic lubricant $320 - $320
9,672
kWh
03 2.4133: Use most efficient type of electric motors $217 $299 $217
6,741
kWh
04 2.4231: Reduce the pressure of compressed air to the minimum required $91 $20 $91
2,638
kWh
TOTAL RECOMMENDED $5,563 $319 $5,563
19,051
kWh
TOTAL IMPLEMENTED $411 $20 $411
12,310
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs