ITAC Assessment: IP7008
ITAC logo
ITAC Assessment: IP7008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product services
NAICS 561499: All Other Business Support Services
SIC 8811: Private Households
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 15,000
ft2
Annual Production 1,000
units
Production Hrs. Annual 2,000
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $205,052 2,635,934
kWh
Natural Gas $10,932 854
MMBtu
Waste Disposal Costs
Water Usage $10,132 142,600
Tgal
TOTAL YEARLY COSTS $226,116
RECOMMENDED SAVINGS* $3,602 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,274 $2,145 $1,274
16,336
kWh
-
02 2.7425: Clean or color roof to reduce solar load $212 $1,194 $212
2,729
kWh
-
03 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $2,116 $24,598 - $2,116
-
MMBtu
TOTAL RECOMMENDED $3,602 $27,937 $1,486
19,065
kWh
$2,116
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs