Assessment Year | 2025 |
---|---|
Principal Product | Bread & Buns |
NAICS | 311812: Commercial Bakeries |
SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
Sales Range | $100 M to 500M |
# of Employees | 155 |
Plant Area |
115,980
ft2
|
Annual Production | 88,000,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $614,313 | 9,510,300 |
kWh
|
$0.065 |
Electricity Demand | $238,828 | 17,798 |
kW-mo/yr
|
$13.42 |
Electricity Fees | $6,368 | - |
|
- |
Natural Gas | $271,347 | 54,969 |
MMBtu
|
$4.94 |
TOTAL YEARLY COSTS | $1,130,856 | |||
RECOMMENDED SAVINGS* | $199,615 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $14,470 | - |
$10,873
167,282
kWh
|
$3,597
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $26,770 | $1,390 |
$26,770
411,840
kWh
|
- | - | |
03 | 2.7233: Use properly designed and sized hvac equipment | $13,579 | $790 |
$8,775
135,000
kWh
|
$4,026
-
kW-mo/yr
|
$778
-
MMBtu
|
|
04 | 2.6218: Turn off equipment when not in use | $6,861 | $128 |
$6,861
105,558
kWh
|
- | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $2,235 | $276 |
$1,679
25,834
kWh
|
$556
-
kW-mo/yr
|
- | |
06 | 2.2437: Recover waste heat from equipment | $33,297 | $5,271 |
$25,876
398,092
kWh
|
$7,421
-
kW-mo/yr
|
- | |
07 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $58,146 | $9,960 |
$43,693
672,198
kWh
|
$14,453
-
kW-mo/yr
|
- | |
08 | 2.4221: Install compressor air intakes in coolest locations | $5,523 | $960 |
$4,292
66,024
kWh
|
$1,231
-
kW-mo/yr
|
- | |
09 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $10,982 | $16,152 | - | - |
$10,982
-
MMBtu
|
|
10 | 2.3212: Optimize plant power factor | $26,546 | $45,576 | - |
$26,546
-
kW-mo/yr
|
- | |
11 | 2.7492: Use proper thickness of insulation on building envelope | $1,206 | $2,279 |
$906
13,938
kWh
|
$300
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $199,615 | $82,782 |
$129,725
1,995,766
kWh
|
$58,130
-
kW-mo/yr
|
$11,760
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs