| Assessment Year | 2024 |
|---|---|
| Principal Product | Gray & Ductile Cast Iron Articles |
| NAICS | 331511: Iron Foundries |
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 116 |
| Plant Area |
255,000
ft2
|
| Annual Production | 16,819
ton
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $581,597 | 18,545,929 |
kWh
|
$0.031 | |
| Electricity Demand | $980,619 | 85,069 |
kW-mo/yr
|
$11.53 | |
| Electricity Fees | $113,027 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $102,836 | 34,866 |
Tgal
|
$2.95 | |
| TOTAL YEARLY COSTS | $1,778,079 | ||||
| RECOMMENDED SAVINGS* | $26,495 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,450 | - |
$1,733
55,886
kWh
|
$3,717
-
kW-mo/yr
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,263 | $354 |
$3,651
117,781
kWh
|
$2,612
-
kW-mo/yr
|
|
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $738 | $180 |
$254
8,190
kWh
|
$484
-
kW-mo/yr
|
|
| 04 | 2.7135: Install occupancy sensors | $692 | $273 |
$692
22,337
kWh
|
- | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $5,389 | $2,562 |
$5,389
173,846
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,963 | $14,490 |
$2,493
80,411
kWh
|
$5,470
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $26,495 | $17,859 |
$14,212
458,451
kWh
|
$12,283
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs