Assessment Year | 2023 |
---|---|
Principal Product | Plastic Film and Sheet |
NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 112 |
Plant Area |
105,000
ft2
|
Annual Production | 8,200,000
units
|
Production Hrs. Annual | 7,400
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $345,973 | 9,225,600 |
kWh
|
$0.038 | |
Electricity Demand | $557,491 | 21,544 |
kW-mo/yr
|
$25.88 | |
Electricity Fees | $3,600 | - |
|
- | |
Natural Gas | $37,261 | 3,733 |
MMBtu
|
$9.98 | |
Waste Disposal Costs | |||||
Water Usage | $8,673 | 1,679 |
Tgal
|
$5.17 | |
TOTAL YEARLY COSTS | $952,998 | ||||
RECOMMENDED SAVINGS* | $60,667 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $5,367 | - |
$2,776
73,044
kWh
|
$2,591
-
kW-mo/yr
|
|
02 | 2.2625: Chill water to the highest temperature possible | $1,771 | - |
$1,605
42,226
kWh
|
$166
-
kW-mo/yr
|
|
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $14,876 | $495 |
$7,494
197,199
kWh
|
$7,382
-
kW-mo/yr
|
|
04 | 2.3132: Recharge batteries on during off-peak demand periods | $6,289 | $660 | - |
$6,289
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,696 | $4,266 |
$13,766
362,275
kWh
|
$12,930
-
kW-mo/yr
|
|
06 | 2.7212: Install or upgrade insulation on hvac distribution systems | $590 | $113 |
$540
14,200
kWh
|
$50
-
kW-mo/yr
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $140 | $33 |
$140
3,663
kWh
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,620 | $564 |
$1,620
42,643
kWh
|
- | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,123 | $6,636 |
$3,123
82,184
kWh
|
- | |
10 | 2.7212: Install or upgrade insulation on hvac distribution systems | $195 | $600 |
$177
4,662
kWh
|
$18
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $60,667 | $13,367 |
$31,241
822,096
kWh
|
$29,426
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs