ITAC Assessment: IP0153
ITAC logo
ITAC Assessment: IP0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Waste Water Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $5
M
to 10
M
# of Employees 22
Plant Area 60,000
ft2
Annual Production 2,555,000
Tgal
Production Hrs. Annual 3,484
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $211,635 4,402,975
kWh
Electricity Demand $165,576 8,246
kW-mo/yr
Electricity Fees $708 -
Natural Gas $11,116 5,856
MMBtu
Waste Disposal Costs
Water Usage $10,800 3,000
Tgal
TOTAL YEARLY COSTS $399,834
RECOMMENDED SAVINGS* $41,194 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7221: Lower temperature during the winter season and vice-versa $2,018 $53 $168
3,490
kWh
- $1,851
-
MMBtu
02 2.7135: Install occupancy sensors $73 $128 $73
1,523
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,112 $6,705 $756
15,745
kWh
$1,356
-
kW-mo/yr
-
04 3.7311: Maintain machines to reduce leaks $36,991 $130,160 $23,516
489,925
kWh
$13,475
-
kW-mo/yr
-
TOTAL RECOMMENDED $41,194 $137,046 $24,512
510,683
kWh
$14,831
-
kW-mo/yr
$1,851
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs