ITAC Assessment: IP0148
ITAC logo
ITAC Assessment: IP0148
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Garage Doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $100
M
to 500
M
# of Employees 751
Plant Area 1,059,000
ft2
Annual Production 605,164
units
Production Hrs. Annual 5,375
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $385,358 10,671,235
kWh
Electricity Demand $56,952 7,263
kW-mo/yr
Electricity Fees $7,893 -
Natural Gas $70,094 23,565
MMBtu
Waste Disposal Costs
Water Usage $11,969 1,361
Tgal
Water Disposal $12,964 1,361
Tgal
TOTAL YEARLY COSTS $545,230
RECOMMENDED SAVINGS* $4,296 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,066

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.6211: Conserve energy by efficient use of vending machines $104 - $80
2,225
kWh
$24
-
kW-mo/yr
02 2.6218: Turn off equipment when not in use $844 - $106
2,936
kWh
$738
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,097 $185 $2,084
57,901
kWh
$1,013
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $126 $504 $126
3,494
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $125 $522 $84
2,338
kWh
$41
-
kW-mo/yr
TOTAL RECOMMENDED $4,296 $1,211 $2,480
68,894
kWh
$1,816
-
kW-mo/yr
TOTAL IMPLEMENTED $4,066 $707 $2,274
63,175
kWh
$1,792
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs