ITAC Assessment: IP0130
ITAC logo
ITAC Assessment: IP0130
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Ice Cream and Milk
NAICS 311520: Ice Cream and Frozen Dessert Manufacturing
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $100
M
to 500
M
# of Employees 400
Plant Area 250,000
ft2
Annual Production 277,059
ton
Production Hrs. Annual 8,346
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,349,125 35,285,600
kWh
Electricity Demand $1,324,136 66,859
kW-mo/yr
Electricity Fees $(-51,364.0) -
Natural Gas $68,827 83,098
MMBtu
TOTAL YEARLY COSTS $2,690,724
RECOMMENDED SAVINGS* $55,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $12,804

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7221: Lower temperature during the winter season and vice-versa $547 - $432
10,794
kWh
- - $115
-
MMBtu
02 2.4231: Reduce the pressure of compressed air to the minimum required $6,064 $70 $3,549
88,715
kWh
$2,515
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,236 $208 $5,236
130,908
kWh
- - -
04 2.3212: Optimize plant power factor $41,119 $18,096 - - $41,119 -
05 2.7135: Install occupancy sensors $539 $348 $539
13,468
kWh
- - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $537 $396 $314
7,845
kWh
$223
-
kW-mo/yr
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $967 $1,966 $565
14,132
kWh
$402
-
kW-mo/yr
- -
TOTAL RECOMMENDED $55,009 $21,084 $10,635
265,862
kWh
$3,140
-
kW-mo/yr
$41,119 $115
-
MMBtu
TOTAL IMPLEMENTED $12,804 $2,640 $9,664
241,600
kWh
$3,140
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs