ITAC Assessment: IP0119
ITAC logo
ITAC Assessment: IP0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Projector screens
NAICS 325992: Photographic Film, Paper, Plate, and Chemical Manufacturing
SIC 3861: Photographic Equipment and Supplies
Sales Range $50
M
to 100
M
# of Employees 325
Plant Area 300,000
ft2
Annual Production 279,215
units
Production Hrs. Annual 4,160
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $227,584 3,000,792
kWh
Electricity Demand $131,889 10,215
kW-mo/yr
Electricity Fees $(-10,402.0) -
Natural Gas $142,459 28,332
MMBtu
TOTAL YEARLY COSTS $491,530
RECOMMENDED SAVINGS* $55,421 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $49,651

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $768 $28 $768
10,130
kWh
- - - -
02 2.7221: Lower temperature during the winter season and vice-versa $2,920 $460 $712
9,384
kWh
- $2,208
-
MMBtu
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,082 $379 $2,082
27,456
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,002 $875 $666
8,786
kWh
$336
-
kW-mo/yr
- - -
05 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $27,937 $38,052 $22,654
298,716
kWh
$5,283
-
kW-mo/yr
- - -
06 2.1224: Replace boiler $20,712 $66,681 - - $3,712
-
MMBtu
$3,000 $14,000
TOTAL RECOMMENDED $55,421 $106,475 $26,882
354,472
kWh
$5,619
-
kW-mo/yr
$5,920
-
MMBtu
$3,000 $14,000
TOTAL IMPLEMENTED $49,651 $105,608 $23,320
307,502
kWh
$5,619
-
kW-mo/yr
$3,712
-
MMBtu
$3,000 $14,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs