Assessment Year | 2019 |
---|---|
Principal Product | Projector screens |
NAICS | 325992: Photographic Film, Paper, Plate, and Chemical Manufacturing |
SIC | 3861: Photographic Equipment and Supplies |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
300,000
ft2
|
Annual Production | 279,215
units
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $227,584 | 3,000,792 |
kWh
|
$0.076 |
Electricity Demand | $131,889 | 10,215 |
kW-mo/yr
|
$12.91 |
Electricity Fees | $(-10,402.0) | - |
|
- |
Natural Gas | $142,459 | 28,332 |
MMBtu
|
$5.03 |
TOTAL YEARLY COSTS | $491,530 | |||
RECOMMENDED SAVINGS* | $55,421 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $49,651 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $768 | $28 |
$768
10,130
kWh
|
- | - | - | - | |
02 | 2.7221: Lower temperature during the winter season and vice-versa | $2,920 | $460 |
$712
9,384
kWh
|
- |
$2,208
-
MMBtu
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,082 | $379 |
$2,082
27,456
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,002 | $875 |
$666
8,786
kWh
|
$336
-
kW-mo/yr
|
- | - | - | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $27,937 | $38,052 |
$22,654
298,716
kWh
|
$5,283
-
kW-mo/yr
|
- | - | - | |
06 | 2.1224: Replace boiler | $20,712 | $66,681 | - | - |
$3,712
-
MMBtu
|
$3,000 | $14,000 | |
TOTAL RECOMMENDED | $55,421 | $106,475 |
$26,882
354,472
kWh
|
$5,619
-
kW-mo/yr
|
$5,920
-
MMBtu
|
$3,000 | $14,000 | ||
TOTAL IMPLEMENTED | $49,651 | $105,608 |
$23,320
307,502
kWh
|
$5,619
-
kW-mo/yr
|
$3,712
-
MMBtu
|
$3,000 | $14,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs