ITAC Assessment: IP0079
ITAC logo
ITAC Assessment: IP0079
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Aluminum Castings
NAICS 331524: Aluminum Foundries (except Die-Casting)
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 168,000
ft2
Annual Production 189,099
pieces
Production Hrs. Annual 4,500
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $481,737 7,255,800
kWh
Electricity Demand $229,514 20,252
kW-mo/yr
Electricity Fees $82,781 -
Natural Gas $341,010 102,958
MMBtu
TOTAL YEARLY COSTS $1,135,042
RECOMMENDED SAVINGS* $193,216 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $97,740

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $5,047 $6 $3,471
52,267
kWh
$1,576
-
kW-mo/yr
- -
02 2.6211: Conserve energy by efficient use of vending machines $3,466 - $2,809
42,311
kWh
$657
-
kW-mo/yr
- -
03 2.7221: Lower temperature during the winter season and vice-versa $35,073 $678 $11,174
168,286
kWh
- - $23,899
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,340 $147 $4,357
65,612
kWh
$1,983
-
kW-mo/yr
- -
05 2.2514: Cover open tanks $20,504 $766 - - - $20,504
-
MMBtu
06 2.7135: Install occupancy sensors $3,135 $302 $3,135
47,210
kWh
- - -
07 2.4322: Use or replace with energy efficient substitutes $12,652 $1,239 $12,652
190,540
kWh
- - -
08 2.4238: Do not use compressed air for personal cooling $742 $90 $742
11,170
kWh
- - -
09 4.812: Apply for investment incentives $38,196 $5,000 - - $38,196 -
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $12,415 $9,367 $12,415
186,975
kWh
- - -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,761 $2,448 $1,210
18,225
kWh
$551
-
kW-mo/yr
- -
12 2.3212: Optimize plant power factor $23,934 $35,575 - - $23,934 -
13 4.812: Apply for investment incentives $2,977 $5,000 - - $2,977 -
14 2.2414: Use waste heat from hot flue gases to preheat $10,861 $3,300 - - - $10,861
-
MMBtu
15 2.7142: Utilize higher efficiency lamps and/or ballasts $16,112 $79,976 $11,074
166,770
kWh
$5,038
-
kW-mo/yr
- -
TOTAL RECOMMENDED $193,216 $143,894 $63,039
949,366
kWh
$9,805
-
kW-mo/yr
$65,107 $55,264
-
MMBtu
TOTAL IMPLEMENTED $97,740 $46,584 $8,570
129,049
kWh
$3,559
-
kW-mo/yr
$65,107 $20,504
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs