ITAC Assessment: GT0575
ITAC logo
ITAC Assessment: GT0575
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Conduit Seal
NAICS
n/a
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 8
Plant Area 20,000
ft2
Annual Production 1,300,000
lb
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,098 207,796
kWh
Natural Gas $2,227 430
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,990 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,250

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.8114: Change rate schedules or other changes in utility service $2,620 - $2,620
-
kWh
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,000 - $1,000
-
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $580 $980 $580
4,982
kWh
04 2.7134: Use photocell controls $670 $59 $670
5,569
kWh
05 2.4133: Use most efficient type of electric motors $120 $232 $120
879
kWh
TOTAL RECOMMENDED $4,990 $1,271 $4,990
11,430
kWh
TOTAL IMPLEMENTED $1,250 $1,039 $1,250
10,551
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs