ITAC Assessment: IP0038
ITAC logo
ITAC Assessment: IP0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Clean Water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 58,285
ft2
Annual Production 5,200,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $462,844 11,203,661
kWh
Electricity Demand $467,959 20,843
kW-mo/yr
Electricity Fees $4,169 -
Natural Gas $28,128 3,871
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $92,917 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,479

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $6,356 $73 - - $6,356
-
MMBtu
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,361 $5,637 $432
10,637
kWh
$3,929
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $43,399 $68,000 $32,488
800,201
kWh
$10,911
-
kW-mo/yr
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,464 $7,184 $600
14,780
kWh
$1,864
-
kW-mo/yr
-
05 2.4133: Use most efficient type of electric motors $32,524 $83,652 $10,110
249,004
kWh
$22,414
-
kW-mo/yr
-
06 2.7241: Install outside air damper / economizer on hvac unit $1,511 $4,122 $1,511
37,206
kWh
- -
07 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,179 $6,803 $667
16,434
kWh
$2,022
-
kW-mo/yr
$(-510.0)
-
MMBtu
08 2.7135: Install occupancy sensors $123 $400 $123
3,025
kWh
- -
TOTAL RECOMMENDED $92,917 $175,871 $45,931
1,131,287
kWh
$41,140
-
kW-mo/yr
$5,846
-
MMBtu
TOTAL IMPLEMENTED $6,479 $473 $123
3,025
kWh
- $6,356
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs