Assessment Year | 2015 |
---|---|
Principal Product | Clean Water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
58,285
ft2
|
Annual Production | 5,200,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $462,844 | 11,203,661 |
kWh
|
$0.041 |
Electricity Demand | $467,959 | 20,843 |
kW-mo/yr
|
$22.45 |
Electricity Fees | $4,169 | - |
|
- |
Natural Gas | $28,128 | 3,871 |
MMBtu
|
$7.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,917 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,479 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $6,356 | $73 | - | - |
$6,356
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,361 | $5,637 |
$432
10,637
kWh
|
$3,929
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $43,399 | $68,000 |
$32,488
800,201
kWh
|
$10,911
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,464 | $7,184 |
$600
14,780
kWh
|
$1,864
-
kW-mo/yr
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $32,524 | $83,652 |
$10,110
249,004
kWh
|
$22,414
-
kW-mo/yr
|
- | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $1,511 | $4,122 |
$1,511
37,206
kWh
|
- | - | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,179 | $6,803 |
$667
16,434
kWh
|
$2,022
-
kW-mo/yr
|
$(-510.0)
-
MMBtu
|
|
08 | 2.7135: Install occupancy sensors | $123 | $400 |
$123
3,025
kWh
|
- | - | |
TOTAL RECOMMENDED | $92,917 | $175,871 |
$45,931
1,131,287
kWh
|
$41,140
-
kW-mo/yr
|
$5,846
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,479 | $473 |
$123
3,025
kWh
|
- |
$6,356
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs