Assessment Year | 2014 |
---|---|
Principal Product | Powder Coating |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
60,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,860 | 1,144,200 |
kWh
|
$0.065 |
Electricity Demand | $31,733 | 5,130 |
kW-mo/yr
|
$6.19 |
Electricity Fees | $12,959 | - |
|
- |
Natural Gas | $123,776 | 21,983 |
MMBtu
|
$5.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,545 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.812: Apply for investment incentives | $6,604 | - | - | - | $6,604 | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,247 | $70 |
$2,247
33,696
kWh
|
- | - | - | |
03 | 2.4322: Use or replace with energy efficient substitutes | $1,175 | $67 |
$586
8,793
kWh
|
$589
-
kW-mo/yr
|
- | - | |
04 | 2.1224: Replace boiler | $47,742 | $25,000 | - | - | - |
$47,742
-
MMBtu
|
|
05 | 2.2511: Insulate bare equipment | $320 | $300 | - | - | - |
$320
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $221 | $286 | - | - | - |
$221
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $553 | $991 |
$79
1,180
kWh
|
$474
-
kW-mo/yr
|
- | - | |
08 | 2.3212: Optimize plant power factor | $5,683 | $16,847 | - |
$5,683
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $64,545 | $43,561 |
$2,912
43,669
kWh
|
$6,746
-
kW-mo/yr
|
$6,604 |
$48,283
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs