| Assessment Year | 2014 |
|---|---|
| Principal Product | Fans |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 91 |
| Plant Area |
60,759
ft2
|
| Annual Production | 400,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $52,770 | 3,135,502 |
kWh
|
$0.017 |
| Electricity Demand | $110,680 | 7,872 |
kW-mo/yr
|
$14.06 |
| Electricity Fees | $134,308 | - |
|
- |
| Natural Gas | $48,987 | 8,267 |
MMBtu
|
$5.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $31,276 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,805 | - | - |
$6,805
-
kW-mo/yr
|
- | - | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $8,161 | - | - | - | $8,161 | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $471 | - |
$226
5,741
kWh
|
$245
-
kW-mo/yr
|
- | - | |
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $4,545 | - |
$1,366
34,756
kWh
|
- | - |
$3,179
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,759 | $60 |
$4,759
121,095
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,468 | - |
$377
9,587
kWh
|
$1,091
-
kW-mo/yr
|
- | - | |
| 07 | 2.2511: Insulate bare equipment | $2,123 | $1,770 | - | - | - |
$2,123
-
MMBtu
|
|
| 08 | 2.7135: Install occupancy sensors | $2,944 | $3,961 |
$2,944
74,905
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $31,276 | $5,791 |
$9,672
246,084
kWh
|
$8,141
-
kW-mo/yr
|
$8,161 |
$5,302
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs