Assessment Year | 2014 |
---|---|
Principal Product | Fans |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 91 |
Plant Area |
60,759
ft2
|
Annual Production | 400,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,770 | 3,135,502 |
kWh
|
$0.017 |
Electricity Demand | $110,680 | 7,872 |
kW-mo/yr
|
$14.06 |
Electricity Fees | $134,308 | - |
|
- |
Natural Gas | $48,987 | 8,267 |
MMBtu
|
$5.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,276 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,805 | - | - |
$6,805
-
kW-mo/yr
|
- | - | |
02 | 2.8121: Apply for tax-free status for energy purchases | $8,161 | - | - | - | $8,161 | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $471 | - |
$226
5,741
kWh
|
$245
-
kW-mo/yr
|
- | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $4,545 | - |
$1,366
34,756
kWh
|
- | - |
$3,179
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,759 | $60 |
$4,759
121,095
kWh
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,468 | - |
$377
9,587
kWh
|
$1,091
-
kW-mo/yr
|
- | - | |
07 | 2.2511: Insulate bare equipment | $2,123 | $1,770 | - | - | - |
$2,123
-
MMBtu
|
|
08 | 2.7135: Install occupancy sensors | $2,944 | $3,961 |
$2,944
74,905
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $31,276 | $5,791 |
$9,672
246,084
kWh
|
$8,141
-
kW-mo/yr
|
$8,161 |
$5,302
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs