| Assessment Year | 2014 |
|---|---|
| Principal Product | Beer |
| NAICS | 312120: Breweries |
| SIC | 2083: Malt |
| Sales Range | $1 M to 5M |
| # of Employees | 21 |
| Plant Area |
40,000
ft2
|
| Annual Production | 4,324
Tgal
|
| Production Hrs. Annual | 4,050
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $10,445 | 620,664 |
kWh
|
$0.017 |
| Electricity Demand | $23,839 | 1,696 |
kW-mo/yr
|
$14.06 |
| Electricity Fees | $48,138 | - |
|
- |
| Natural Gas | $31,474 | 4,009 |
MMBtu
|
$7.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $17,391 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,439 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Gaseous Waste Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.812: Apply for investment incentives | $4,267 | - | - | - | - | - | - | $4,267 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,655 | - | - | - | - |
$2,655
-
lb
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $513 | - |
$188
5,144
kWh
|
$325
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 4.821: Pay bills on time to avoid late fees | $1,181 | - | - | - | - | - | - | $1,181 | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $3,336 | - |
$1,225
33,461
kWh
|
$2,111
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7135: Install occupancy sensors | $222 | $118 |
$222
6,067
kWh
|
- | - | - | - | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $349 | $231 | - | - |
$349
-
MMBtu
|
- | - | - | |
| 08 | 2.4239: Eliminate or reduce compressed air usage | $4,868 | $5,580 |
$476
13,000
kWh
|
$(-608.0)
-
kW-mo/yr
|
- | - | $5,000 | - | |
| TOTAL RECOMMENDED | $17,391 | $5,929 |
$2,111
57,672
kWh
|
$1,828
-
kW-mo/yr
|
$349
-
MMBtu
|
$2,655
-
lb
|
$5,000 | $5,448 | ||
| TOTAL IMPLEMENTED | $9,439 | $5,698 |
$886
24,211
kWh
|
$(-283.0)
-
kW-mo/yr
|
- |
$2,655
-
lb
|
$5,000 | $1,181 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Gaseous Waste Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs