ITAC Assessment: IP0021
ITAC logo
ITAC Assessment: IP0021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Beer
NAICS 312120: Breweries
SIC 2083: Malt
Sales Range $1
M
to 5
M
# of Employees 21
Plant Area 40,000
ft2
Annual Production 4,324
Tgal
Production Hrs. Annual 4,050
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $10,445 620,664
kWh
Electricity Demand $23,839 1,696
kW-mo/yr
Electricity Fees $48,138 -
Natural Gas $31,474 4,009
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,391 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,439

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Gaseous Waste Savings Personnel Changes Savings Administrative Changes Savings
01 4.812: Apply for investment incentives $4,267 - - - - - - $4,267
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,655 - - - - $2,655
-
lb
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $513 - $188
5,144
kWh
$325
-
kW-mo/yr
- - - -
04 4.821: Pay bills on time to avoid late fees $1,181 - - - - - - $1,181
05 2.7111: Reduce illumination to minimum necessary levels $3,336 - $1,225
33,461
kWh
$2,111
-
kW-mo/yr
- - - -
06 2.7135: Install occupancy sensors $222 $118 $222
6,067
kWh
- - - - -
07 2.2136: Install / repair insulation on steam lines $349 $231 - - $349
-
MMBtu
- - -
08 2.4239: Eliminate or reduce compressed air usage $4,868 $5,580 $476
13,000
kWh
$(-608.0)
-
kW-mo/yr
- - $5,000 -
TOTAL RECOMMENDED $17,391 $5,929 $2,111
57,672
kWh
$1,828
-
kW-mo/yr
$349
-
MMBtu
$2,655
-
lb
$5,000 $5,448
TOTAL IMPLEMENTED $9,439 $5,698 $886
24,211
kWh
$(-283.0)
-
kW-mo/yr
- $2,655
-
lb
$5,000 $1,181
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Gaseous Waste Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs