ITAC Assessment: IP0018
ITAC logo
ITAC Assessment: IP0018
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product clay coated recycled paperboard
NAICS 322130: Paperboard Mills
SIC 2621: Paper Mills
Sales Range $50
M
to 100
M
# of Employees 194
Plant Area 470,000
ft2
Annual Production 137,000
ton
Production Hrs. Annual 8,640
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,619,673 101,840,657
kWh
Electricity Demand $1,742,920 160,935
kW-mo/yr
Electricity Fees $2,972,292 -
Natural Gas $3,279,791 995,590
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $267,615 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $216,518

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 4.812: Apply for investment incentives $42,227 - - - - $42,227
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $109,212 - $64,974
1,866,240
kWh
$44,238
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,467 $430 $1,468
42,163
kWh
$999
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $734 $100 $734
21,082
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,545 $1,400 $7,545
216,709
kWh
- - -
06 2.2511: Insulate bare equipment $5,669 $2,019 - - $5,669
-
MMBtu
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $99,761 $59,384 $54,295
1,559,520
kWh
$45,466
-
kW-mo/yr
- -
TOTAL RECOMMENDED $267,615 $63,333 $129,016
3,705,714
kWh
$90,703
-
kW-mo/yr
$5,669
-
MMBtu
$42,227
TOTAL IMPLEMENTED $216,518 $60,784 $126,814
3,642,469
kWh
$89,704
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs