Assessment Year | 2025 |
---|---|
Principal Product | Nickel and Chromium Electroplating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 80 |
Plant Area |
206,000
ft2
|
Annual Production | 123,143
ton
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $849,025 | 8,815,152 |
kWh
|
$0.096 | |
Electricity Demand | $446,667 | 23,539 |
kW-mo/yr
|
$18.98 | |
Electricity Fees | $31,003 | - |
|
- | |
Natural Gas | $220,785 | 106,210 |
MMBtu
|
$2.08 | |
Waste Disposal Costs | |||||
Water Usage | $146,408 | 12,460 |
Tgal
|
$11.75 | |
TOTAL YEARLY COSTS | $1,693,887 | ||||
RECOMMENDED SAVINGS* | $105,657 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,206 | $226 |
$1,461
15,218
kWh
|
$745
-
kW-mo/yr
|
- | |
02 | 2.1133: Adjust burners for efficient operation | $11,584 | $631 | - | - |
$11,584
-
MMBtu
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,276 | - |
$3,136
32,664
kWh
|
$140
-
kW-mo/yr
|
- | |
04 | 2.2511: Insulate bare equipment | $1,870 | $5,460 | - | - |
$1,870
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,732 | $1,026 |
$1,661
17,304
kWh
|
$71
-
kW-mo/yr
|
- | |
06 | 2.2135: Repair and eliminate steam leaks | $5,105 | $1,367 | - | - |
$5,105
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $696 | $288 |
$461
4,800
kWh
|
$235
-
kW-mo/yr
|
- | |
08 | 2.3212: Optimize plant power factor | $77,211 | $108,749 | - |
$77,211
-
kW-mo/yr
|
- | |
09 | 2.2511: Insulate bare equipment | $1,978 | $756 | - | - |
$1,978
-
MMBtu
|
|
TOTAL RECOMMENDED | $105,657 | $118,504 |
$6,719
69,986
kWh
|
$78,402
-
kW-mo/yr
|
$20,536
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs