| Assessment Year | 2007 |
|---|---|
| Principal Product | Corrugated containers |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 215 |
| Plant Area |
430,000
ft2
|
| Annual Production | 360,000,000
thousand feet
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $135,710 | 3,744,021 |
kWh
|
$0.036 |
| Electricity Demand | $139,360 | 9,565 |
kW-mo/yr
|
$14.57 |
| Electricity Fees | $1,000 | - |
|
- |
| Natural Gas | $260,512 | 38,531 |
MMBtu
|
$6.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,291 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,961 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2121: Increase amount of condensate returned | $13,760 | $90,000 | - | - |
$13,760
-
MMBtu
|
|
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,870 | $48,000 | - | - |
$4,870
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,760 | $500 |
$1,900
55,400
kWh
|
$860
-
kW-mo/yr
|
- | |
| 04 | 2.1213: Direct warmest air to combustion intake | $1,240 | $230 | - | - |
$1,240
-
MMBtu
|
|
| 05 | 2.4133: Use most efficient type of electric motors | $201 | $277 |
$105
3,081
kWh
|
$96
-
kW-mo/yr
|
- | |
| 06 | 2.9114: Use solar heat to make electricty | $1,460 | $11,000 |
$500
14,600
kWh
|
$960
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $24,291 | $150,007 |
$2,505
73,081
kWh
|
$1,916
-
kW-mo/yr
|
$19,870
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,961 | $777 |
$2,005
58,481
kWh
|
$956
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs