Assessment Year | 2025 |
---|---|
Principal Product | Electroless Nickel and Chrome Plating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
25,735
ft2
|
Annual Production | 9,000,000
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $49,348 | 866,449 |
kWh
|
$0.057 | |
Electricity Demand | $23,185 | 2,034 |
kW-mo/yr
|
$11.40 | |
Electricity Fees | $31,397 | - |
|
- | |
Natural Gas | $66,760 | 9,737 |
MMBtu
|
$6.86 | |
Waste Disposal Costs | |||||
Water Usage | $6,190 | 446 |
Tgal
|
$13.87 | |
TOTAL YEARLY COSTS | $176,880 | ||||
RECOMMENDED SAVINGS* | $76,098 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $34,094 | $58,119 |
$3,059
53,667
kWh
|
$2,827
-
kW-mo/yr
|
$28,208
-
MMBtu
|
|
02 | 2.3312: Install efficient rectifiers | $8,079 | $8,129 |
$4,194
73,895
kWh
|
$3,885
-
kW-mo/yr
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,138 | $5,309 |
$13,430
235,606
kWh
|
$(-291.8)
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,318 | $7,240 |
$7,318
128,386
kWh
|
- | - | |
05 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $4,795 | $3,414 | - | - |
$4,795
-
MMBtu
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,350 | $246 |
$1,222
21,438
kWh
|
$1,128
-
kW-mo/yr
|
- | |
07 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $2,149 | $5,256 | - | - |
$2,149
-
MMBtu
|
|
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,716 | - |
$915
16,049
kWh
|
$802
-
kW-mo/yr
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,137 | - |
$591
10,373
kWh
|
$545
-
kW-mo/yr
|
- | |
10 | 2.4239: Eliminate or reduce compressed air usage | $1,175 | $2,940 |
$760
13,338
kWh
|
$414
-
kW-mo/yr
|
- | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $149 | $144 |
$79
1,388
kWh
|
$69
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $76,098 | $90,796 |
$31,568
554,140
kWh
|
$9,379
-
kW-mo/yr
|
$35,151
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs