ITAC Assessment: IC0301
ITAC logo
ITAC Assessment: IC0301
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Aggregate Equipment
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $50
M
to 100
M
# of Employees 85
Plant Area 55,000
ft2
Annual Production 80
units
Production Hrs. Annual 4,420
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,616 945,421
kWh
Electricity Demand $29,592 2,919
kW-mo/yr
Electricity Fees $1,885 -
Natural Gas $41,193 6,488
MMBtu
Waste Disposal Costs
Water Usage $3,277 170
Tgal
TOTAL YEARLY COSTS $111,563
RECOMMENDED SAVINGS* $81,101 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $24,209 $186,605 $9,480
249,478
kWh
$14,728
-
kW-mo/yr
- -
02 3.5316: Contract a wood pallet recycling company $26,388 $3,600 - - - $26,388
03 2.4239: Eliminate or reduce compressed air usage $2,886 $205 $80
2,096
kWh
$2,806
-
kW-mo/yr
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,652 - $2,697
70,984
kWh
$1,954
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,042 $205 $91
2,406
kWh
$1,950
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,487 - $2,602
68,466
kWh
$1,885
-
kW-mo/yr
- -
07 2.5113: Use direct flame impingement or infrared processing for chamber type heating $13,766 $3,820 $(-185.0)
(-4,875)
kWh
$(-912.0)
-
kW-mo/yr
$14,863
-
MMBtu
-
08 2.1115: Eliminate combustible gas in flue gas $2,673 $890 - - $2,673
-
MMBtu
-
TOTAL RECOMMENDED $81,101 $195,324 $14,765
388,555
kWh
$22,412
-
kW-mo/yr
$17,536
-
MMBtu
$26,388
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs